VIC Payment and Review Rights for Landowners Affected by Electricity Transmission Lines

National Electricity (Victoria) Amendment (VicGrid) Bill 2024

Legislative Assembly

Legislative Council

Assent

Share this bill

Introduced by: The Hon Ingrid Stitt MLC (ALP); Lily D'Ambrosio MP (ALP)

Links to official parliament websites

Official page: progress through parliament

Effects of this bill

If this bill passes, it means that:

People with interests in non-public land can apply to the CEO VicGrid to be determined as eligible for payments regarding transmission interests.
People who hold a legal interest in public land (of a type defined by regulation for transmission access) can apply to the Energy Minister to be determined as eligible for payments.
The CEO VicGrid must provide an initial payment to eligible non-public land holders, with rates set at $8,000 or $16,000 per kilometre depending on the width of the interest.
The CEO VicGrid must make subsequent annual payments to eligible non-public land holders for up to 23 years.
People affected by a CEO VicGrid decision can apply to the Victorian Civil and Administrative Tribunal (VCAT) for a review within 28 days.
Transmission companies must notify the CEO VicGrid or the Energy Minister within 15 business days if they stop holding a relevant transmission interest.
Eligible public land holders must notify the Energy Minister within 15 business days if they are no longer eligible for payments.
The Energy Minister or CEO VicGrid can recover overpayments made to ineligible people as a debt due to the Crown.